Board Selects Vendors for Phase One Construction
Feb. 12, 2020
The Lindbergh Schools Board of Education voted on Feb. 11 to approve the first phase of the Lindbergh High School construction project, which includes construction of a central utility building, demolition of the math building and high school main office, installation of utilities, additional exterior site improvements, and asbestos abatement.
Six vendors bid on the earthwork, phase one demolition and utility package. The best qualified complete bid was submitted by Wachter Inc. for $2,704,500. In a separate bid, six companies submitted proposals for the asbestos abatement work. The best qualified complete bid for that project was submitted by Talbert, for $90,733. Total cost for this first phase of construction will be $2,795,233.
LHS construction will take place in three phases, with phase one beginning in spring and summer of 2020.
The bid package for phase two will be approved in March, with construction beginning in summer 2020. Phase two will include construction of a new three-story structure that will connect existing buildings on the high school campus, in addition to renovation and remodeling work in existing buildings. This work is scheduled for completion in January 2023.
Phase three is scheduled to begin in January 2023 and will include demolition of the current auditorium and 300s/400s building, and resurfacing and reconfiguration of on-campus parking areas.